You want to firm several planned production orders with same start date. A certain work center (e.g. Lathe-1) is used in every route. The firmed production orders got scheduled with different start dates.
Verify if the capacity is overloaded. If yes, job scheduling tries to schedule back and forth and back and forth until loop limit is reached. The error message "Attempts are made to schedule production before today's date or before materials are available." indicates not only material...(read more)
↧